Inventory planning

Safety Stock & Reorder Point Planner

Turn demand variability, supplier lead time, and service-level targets into a practical inventory policy for one SKU.

Demand & replenishment inputs

Statistical planning model. This version treats demand and lead-time variability as independent and uses cycle service level as the target. Use inputs measured in matching daily units.
Service-level sensitivity

See the inventory cost of a higher service target.

Using the same demand and lead-time inputs, compare how much buffer inventory changes as the cycle service target rises.

Continue the inventory workflow

ABC / Cycle Count Prioritization

Rank a SKU population by annual consumption value, then layer in activity and discrepancy history to focus control effort.

Continue to ABC / Cycle Count →
Inventory planning guide

Safety stock and reorder point: what the calculator is estimating

Safety stock is inventory held to absorb uncertainty in demand and replenishment. The reorder point is the inventory position at which replenishment should be triggered based on expected demand during lead time plus the selected safety buffer.

Use this planner to test how demand variability, supplier lead-time variability, and service-level targets change the recommended buffer. The result is a planning input, not a substitute for supplier constraints, minimum order quantities, shelf life, storage limits, or purchasing judgment.

Next: prioritize the SKU population with ABC and cycle count analysis →

What is the difference between safety stock and reorder point?

Safety stock is a buffer for demand and replenishment uncertainty. The reorder point adds that buffer to expected demand during lead time. Use a consistent demand unit and time basis. This calculator uses demand and lead-time variability with a cycle-service target; it is a planning model, not a guarantee against stockouts. Supplier constraints, unusual demand, shelf life, and inventory-record accuracy still matter.

Formula

Safety stock = z × √(L × σd² + d² × σL²). Reorder point = d × L + safety stock. Here d is average daily demand, L is average lead time in days, σd and σL are their standard deviations, and z corresponds to the cycle-service target. Displayed stock quantities round up.

Worked example

With daily demand 100 units, daily standard deviation 20, fixed lead time 10 days, and a 95% cycle-service target (z ≈ 1.645), safety stock rounds up to 105 units and the reorder point to 1,105 units.

Common questions

Is the reorder point the order quantity?

No. It is the replenishment trigger; order quantity is a separate policy decision.

Does 95% service mean a 95% fill rate?

Not here. The target is cycle service: the probability of avoiding a stockout during a replenishment cycle under the model assumptions.

What if lead time is fixed?

Enter zero lead-time variability. Demand variability can still create a need for safety stock.