Dock Capacity & Appointment Planning
Translate the day’s inbound and outbound schedule into dock-door hours, then compare the workload with the door capacity you actually have available.
Dock assumptions
See what is consuming the dock window.
Inbound and outbound work are converted to door-hours so different service times can be compared on the same capacity scale.
See how much buffer you are choosing to keep.
Compare the same schedule at several target utilization levels. Higher planned utilization uses the doors harder but leaves less room for late arrivals, long unloads, paperwork delays, and other day-to-day variation.
Labor & Capacity Planning
You can now move from staffing requirements to storage headroom and dock-door capacity. The next major build can start a new workflow or deepen one of the existing branches.
Convert the inbound and outbound schedule into dock-door hours
Dock capacity depends on more than the number of physical doors. Planned loads, average service time, the appointment window, buffer time, and target utilization determine how many door-hours are available and how many are required.
Use the utilization sensitivity view to see the tradeoff between running doors harder and preserving room for late arrivals, paperwork, long unloads, congestion, and other operating variation.
How many dock doors do I need?
Estimate the door-hours required by your planned loads, including service time and any per-load buffer. Divide that workload by the hours one door can provide at your chosen utilization target, then round up. Shared doors pool inbound and outbound demand; dedicated doors must be planned separately. The result is a planning estimate, not a queueing or appointment simulation, so peak congestion still needs review.
Formula
Required door-hours = Σ(loads × (service minutes + buffer minutes) ÷ 60). Shared doors needed = ceiling(required door-hours ÷ (planning-window hours × target utilization)). For dedicated doors, calculate inbound and outbound requirements separately and add the rounded results.
Worked example
Twenty loads taking 60 minutes each, including buffer, need 20 door-hours. Over an 8-hour window at an 80% utilization target, each door supplies 6.4 planning hours. ceiling(20 ÷ 6.4) = 4 shared doors.
Common questions
Why not plan every door at 100%?
A lower target can leave room for variability, breaks in flow, and delays; the appropriate target depends on the operation.
Are inbound and outbound doors interchangeable?
Only in shared mode. Dedicated-mode demand is evaluated against the respective door pool.
Does this predict truck waiting time?
No. Arrival patterns, labor, equipment, staging, and appointment congestion need separate assessment.